Milestones
List view
Goal: Docs refresh, release automation, clean-machine verification. Exit: v1.0.0 tag; README quick-start verified on a clean machine. Plan: docs/22 (roadmap).
Due by March 5, 2027•1/5 issues closedGoal: EXP-01…EXP-07 executed, experiment reports, hardening, operations readiness. Exit: SC-1…SC-6 assessed (pass or honestly reported). Plan: docs/22 (roadmap).
Due by February 26, 2027•5/16 issues closedGoal: Gazebo image, roboprobe_ros nodes, adapter, sim tests. Exit: Gazebo nightly green; backend contract suite passes on Gazebo. Plan: docs/22 (roadmap).
Due by February 12, 2027•8/17 issues closedGoal: All MVP screens in the Field Notebook design, production web image, E2E. Exit: Playwright flows + axe green. Plan: docs/22 (roadmap).
Due by January 29, 2027•29/29 issues closedGoal: REST + SSE complete per doc 12. Exit: OpenAPI snapshot committed; schemathesis clean. Plan: docs/22 (roadmap).
Due by January 15, 2027•20/20 issues closedGoal: Clustering, SHAP, rules, interaction test, risk maps, report v1, k2d reference set. Exit: HTML report for a k2d campaign. Plan: docs/22 (roadmap).
Due by January 8, 2027•18/18 issues closedGoal: RobustnessGP, S-BO, S-LSE, S-PROBE. Exit: doc 07 §9 benchmark gates pass. Plan: docs/22 (roadmap).
Due by January 1, 2027•16/16 issues closedGoal: RANDOM/LHS/SOBOL/GRID/OFAT, metrics MET-01..06, statistics, experiment runner. Exit: Analytic (EXP-02-style) experiment runs end-to-end; metric unit tests green. Plan: docs/22 (roadmap).
Due by December 18, 2026•11/11 issues closedGoal: Verdicts, queue, workers, persistence, CLI `campaign run --inline`; k2d calibration. Exit: 100-run S-RANDOM campaign end-to-end in CI; calibration test shows GT-A…D. Plan: docs/22 (roadmap).
Due by December 11, 2026•41/41 issues closedGoal: Space loading, sampling, kinematic2d backend with designed mechanisms; Gazebo feasibility spike (T-090) in parallel. Exit: k2d episode ≤ 2 s; Gazebo spike evidence recorded. Plan: docs/22 (roadmap).
Due by December 4, 2026•27/28 issues closedGoal: Skeleton, settings, logging, CI, compose with Postgres. Exit: `make setup && make test` green on CI; `make up` starts the empty stack. Plan: docs/22 (roadmap).
Due by November 27, 2026•25/25 issues closed