A public, reproducible legacy modernization: Java 8 / Spring Boot 1.5 / AngularJS 1.8 → Java 25 / Spring Boot 4.1 / Angular 22 — safety net first, honest numbers, reusable German migration playbook.

Status: stages 0–5 done; stage 6 (operations and hardening) in progress. The modern stand runs Spring Boot 4.1.0 / Java 25 with an Angular 22 UI, migrated route by route via Strangler Fig, the same Selenium scenarios green on the old AND the new UI — functionally equivalent to the frozen 2016 stand for all legitimate inputs (the deliberate divergences — security fix, absorbed admin page, fixed "undefined" alert — are registered and pinned per stand in ADR-0004). G6 closed (2026-08-02): measured AI test generation, protocol frozen before anything ran (tag ai-testgen-protocol-v1), 24 calls for €0.65, both phases measured in ai-testgen/REPORT.md. The result is the unflattering one: as generated, 12 of 24 classes compiled and looked perfect (100 % coverage, 99.2 % mutation score); after repair brought 21 of 24 green, the same metrics fell to 90.5 % line / 73.2 % mutation — the perfect figures had been computed only over the cells that happened to compile, i.e. the easy ones. Survivorship bias, measured and published rather than quietly kept. Six repaired test classes were adopted into modern/ (88 methods, ADR-0011), lifting its coverage 37 % → 81 %. Stage 6 is not finished, and the honest half of that is: nothing is deployed. No server, no domain, no TLS, no backups — the tag stage-6-cloud-ops does not exist and there is no v1.0.0 release. What stage 6 has delivered, measured, is in Where stage 6 stands. Progress: stages.md · docs/worklog.md.

Why this exists

Companies and institutes sit on Java-8/Spring-Boot-1.x/AngularJS applications (AngularJS EOL since January 2022, Spring Boot 1.x EOL since 2019). Migrations get postponed because legacy systems have no tests, the risk feels incalculable, and vendors demand blind trust. This repository shows — publicly, step by step, with measured effort numbers — how such a migration is de-risked:

  1. Safety net before anything else: a Selenium E2E suite and characterization tests define functional equivalence before the first migration commit — and must stay green through every stage.
  2. Reproducible stages: every stage is a git tag; checkout → docker compose up → working application. See stages.md.
  3. Measured AI-assisted test generation (G6, closed 2026-08-02): LLM-generated unit tests for the same six classes twice — once as 2016 legacy, once as their migrated counterparts — evaluated with JaCoCo coverage and PIT mutation scores under a protocol that was frozen before the first API call (ai-testgen/PROTOCOL.md, tag ai-testgen-protocol-v1). Both phases are measured and reported in ai-testgen/REPORT.md, including the finding that the flattering Phase-A numbers were survivorship bias. Failures stay in the repo.
  4. A German migration playbook (playbook/) with honest effort figures and decision rules, reusable for real projects.

How this was built — read this before reusing any number

The execution was AI-assisted: a Claude Code agent performed the work, directed and reviewed by the owner. This is disclosed here, at the front door, because it changes how the numbers transfer:

  • The logged hours are agent wall-clock time under supervision — the five backend stages took ~4 wall-clock hours on 2026-07-30, against a human-team plan estimate of ~5 focused weeks (docs/MILESTONES.md). Do not price a human migration from these hours; price the method (stage order, safety-net-first, break catalogue) and see the playbook's separately labelled experience-based estimates.
  • What does transfer: the migration path, the breaks the net caught and how, the decision rules, the tooling evaluations (e.g. OpenRewrite's catch/miss list) — those are properties of the stacks, not of who typed.
  • Review model: solo maintainer; "owner reviewed" means author-is-reviewer, hardened by commissioned adversarial reviews whose findings are public (worklog session 7) and were remediated in the open (ADR-0008).
  • The app is small on purpose: ~1.7k LOC backend, 25 REST endpoints, 10 views — big enough to exhibit real breaks, small enough to stay fully honest. Scaling caveats are in every playbook chapter.

Architecture

Two stands run side by side on one machine, and one safety net drives both. That is the whole trick: equivalence is not argued, it is executed against the old and the new system with the same scenarios.

flowchart TB
    subgraph NET["Safety net — the same scenarios against both stands"]
        E2E["e2e/ · Selenium 4<br/>34 scenarios, selector map per UI"]
        CHAR["characterization/ · golden masters<br/>47 tests: HTTP responses + DB state"]
    end

    subgraph LEG["legacy/ · the exhibit, frozen 2016"]
        LAPP["WerkstattCRM WAR<br/>Java 8 · Boot 1.5.22 · AngularJS 1.8<br/>localhost:8080"]
        LDB[("PostgreSQL 9.6<br/>127.0.0.1:5433<br/>init scripts")]
        LAPP --> LDB
    end

    subgraph MOD["modern/ · the migrated stand"]
        MAPP["WerkstattCRM JAR<br/>Java 25 · Boot 4.1 · Angular 22<br/>localhost:8090"]
        MDB[("PostgreSQL 18<br/>127.0.0.1:5434<br/>schema + seed via Flyway")]
        MAPP --> MDB
    end

    EDGE["OPTIONAL · Traefik edge · localhost:8091<br/>Basic auth, security headers, rate limit<br/>compose overlay, off by default"]
    OTEL["OPTIONAL · grafana/otel-lgtm · localhost:3000<br/>traces, metrics, logs<br/>compose profile, off by default"]

    E2E --> LAPP
    E2E --> MAPP
    CHAR --> LAPP
    CHAR --> MAPP
    EDGE -.-> MAPP
    MAPP -.->|"OTLP"| OTEL

    classDef optional stroke-dasharray: 6 4
    class EDGE,OTEL optional
Loading

Reading notes, because two details in that picture are load-bearing:

  • The databases are deliberately different versions. Legacy keeps PostgreSQL 9.6 for ever — it is the exhibit, end-of-life included. Only the modern stand moved to 18 (stage 6). What that costs and what it caught is below.
  • The two optional boxes are genuinely optional. Neither is part of the quickstart: the edge is a separate compose overlay, observability a compose profile. The safety net targets the application ports directly, so the edge is not in the equivalence path by default. That is a default and not an enforced invariant — the suite accepts a -DbaseUrl, and pointing it at the edge on purpose is exactly how the CSP finding below was produced.

Stages

Git tags are first-class deliverables: git checkout <tag>docker compose up → working application. Long form, including what broke in each stage: stages.md.

Tag What it delivers Playbook chapter Status
stage-0-legacy WerkstattCRM as found: Java 8, Boot 1.5.22, AngularJS 1.8.2, JSP admin page, PostgreSQL 9.6, no tests Ausgangslage in ch. 1 done (2026-07-30)
stage-1-safety-net Selenium E2E suite + characterization tests green against legacy; CI gates active — from here on no commit may break them Kap. 1 done (2026-07-30)
stage-2-jdk-build modern/ bootstrapped as a faithful copy running side by side; logging unified; JDK deliberately NOT raised yet Kap. 2 done (2026-07-30)
stage-3-boot-2.7 Boot 1.5.22 → 2.7.18 + Java 17; three real breaks, one of them invisible in the UI and caught only by the golden master Kap. 3 done (2026-07-30)
stage-4-boot-4x Boot 2.7 → 3.5 → 4.1 + Java 25; OpenRewrite used AND evaluated; SQL-injection wart closed as a registered divergence Kap. 4 done (2026-07-30)
stage-5-angular AngularJS → Angular 22.1.0 via Strangler Fig on a URL seam, no ngUpgrade; JSP admin page absorbed; WAR → JAR Kap. 5 done (2026-07-31)
stage-6-cloud-ops Operations and hardening: PostgreSQL 18, Flyway, Actuator health probes, OTel, edge auth, load baseline — deployment still open Kap. 7 in progress (G7) — ops half measured 2026-08-05; tag not created

The AI test-generation experiment (G6) is not a migration stage; it carries one tag of its own, ai-testgen-protocol-v1, which is a pre-registration marker, not a checkout-and-run state, and its results live in ai-testgen/ and Kap. 6. That chapter is why the numbering runs one ahead of the stages from here on: a non-stage milestone took chapter 6, so stage 6 gets chapter 7. Renaming it quietly would have been the easier and the more dishonest option.

Where stage 6 stands (measured 2026-08-05)

Everything in this section was measured on one machine on 2026-08-05 and is written down with its caveats in docs/worklog.md; the decisions have ADRs (0012–0015) in docs/adr/.

Delivered

  • PostgreSQL 9.6 → 18 on the modern stand, legacy untouched. The safety net saw no change: characterization 47/47 green against both stands, and /api/bericht/topkunden — the one endpoint whose raw DB types reach JSON — answers byte-identically on both, decimal literals included. The trap on the way is the interesting part: postgres:18-alpine reports datcollate=en_US.utf8 and sorts in C order anyway (musl accepts the locale name and ignores it). A review step that reads the setting passes while every sorted list in the application silently changes order. The stand therefore runs postgres:18, not -alpine, and there is now a test that sorts instead of asking.
  • Schema and demo seed via Flyway instead of a mounted init script. Measured failure on the way, kept in the repo: in Boot 4, flyway-core alone migrates nothing — the app starts, then dies later on relation "kunde" does not exist. Silent, not loud. spring-boot-starter-flyway is the missing piece. The CI drift guard was rewritten (scripts/check-schema-drift.sh) so a deleted file fails loudly instead of turning the guard green; verified with a negative control.
  • Health that tells the truth. Actuator exposes health and info and nothing else (/env, /beans, /mappings, /metrics, /loggers, /heapdump measured as 404). The default readiness group does not contain the database: with the DB stopped, readiness answered 200 UP while /actuator/health answered 503. After the fix and a corrected retry budget, measured end to end: the container goes unhealthy 25 s after the database dies and healthy again 6 s after it returns. The old TCP probe never noticed at all. Liveness deliberately still ignores the database — a DB outage must not restart a healthy application.
  • Structured logs and tracing: ECS JSON in the container only (a bare java -jar stays human-readable), log↔trace correlation measured working after renaming Micrometer's MDC keys to the ECS field names. Tracing is off by default; the observability profile starts a single grafana/otel-lgtm container for a local demonstration.
  • Security at the edge (optional Traefik overlay): Basic auth in front of /admin, /api/admin and /actuator, security headers, per-IP rate limit. Verified by modern/edge/verify-edge.sh: unauthenticated → 401 on all four protected paths, authenticated → 200, public surface unaffected, and 200 concurrent requests → 103–173 × 429 over five runs through the edge versus 0 × 429 straight at the application.
  • A load baseline, one scenario (load/k6/lesepfad.js, 5 VUs, 45 s, 1146 requests per stand, 0 failures). The result is the unflattering one: the modernisation is not measurably faster — p(95) 1.60 ms modern versus 1.56 ms legacy. Ten years of framework and JDK versions bought supportability, security and a labour market, not speed on this workload. Anyone selling a migration on performance should measure first.
  • A gap in the safety net itself, found and closed. The E2E suite silently ignored -Dstand=modern and ran green against the legacy stand. Same class of bug the characterization side fixed one session earlier — a guard on one side of a symmetric mistake is half a guard. Both flags are now validated eagerly and the wrong one aborts the run.

Not delivered

  • No deployment happened. There is no host, no Dokploy project, no domain, no TLS, no pg_dump schedule and no published image. The repository has no GitHub secrets at all, so a deploy workflow would fail at runtime — none was written, rather than committing one that cannot run.
  • Therefore the tag stage-6-cloud-ops does not exist and v1.0.0 is not released. Stage 6 is in progress, and saying otherwise would be exactly the smoothing this repository exists to argue against.
  • OAuth2/OIDC, an audit log and Angular's CSP_NONCE remain owner-scoped in docs/DEVIATIONS.md. Basic auth at the edge is a lock on the one door that deletes data, not an identity system, and it is described as such.

Repository layout

Directory Content
legacy/ WerkstattCRM as found (2016-era, deliberately untested) — the exhibit
modern/ The migrated application, growing stage by stage; since stage 6 also the edge overlay (modern/edge/)
e2e/ Selenium 4 suite — same scenarios vs. both UIs via selector maps
characterization/ Golden-master tests = the definition of functional equivalence
ai-testgen/ Pre-registered AI test-generation experiment (G6) — protocol, harness, runs and the full report of both phases
load/ k6 read-path scenario, run against both stands (one scenario, by design)
scripts/ Repository guards used by CI, e.g. the schema-drift check
playbook/ German playbook, one chapter per stage
docs/ PRD, SPEC, milestones, ADRs, worklog, deviations ledger, glossary, deployment and manual-task docs

Quickstart

Needs only Docker with the Compose plugin — the applications build inside Docker.

docker compose -f legacy/docker-compose.yml up -d --wait
# SPA: http://localhost:8080 · JSP admin: http://localhost:8080/admin
docker compose -f modern/docker-compose.yml up -d --wait
# modern stand: http://localhost:8090

--wait blocks until the healthchecks pass. Without it the containers are merely running — PostgreSQL is not yet accepting connections, and the next test run fails on timing.

The two optional add-ons stay off unless asked for:

# observability: Grafana + Prometheus + Tempo + Loki in one container, on 127.0.0.1:3000
WERKSTATT_TRACING_ENABLED=true \
  docker compose -f modern/docker-compose.yml --profile observability up -d --wait

# reverse proxy with Basic auth, security headers and rate limiting, on :8091
MODERN_ADMIN_AUTH='admin:$apr1$...' \
  docker compose -f modern/docker-compose.yml -f modern/docker-compose.edge.yml up -d --wait

Everything else — prerequisites per module, resetting the database, troubleshooting — is in docs/deployment.md. The by-hand steps are checklisted in docs/MANUAL_TASKS.md.

Testing

The safety net is the product's spine, so it is one command per suite, and both stands must answer the same way:

# characterization — the equivalence gate (47 tests per stand)
./mvnw verify -f characterization/pom.xml
./mvnw verify -f characterization/pom.xml \
  -DbaseUrl=http://localhost:8090 -DdbUrl=jdbc:postgresql://localhost:5434/werkstatt -Dstand=modern

# Selenium E2E (34 scenarios per stand)
./mvnw verify -f e2e/pom.xml -Dtarget=legacy
./mvnw verify -f e2e/pom.xml -Dtarget=modern

# modern module build incl. Angular, lint/format gates and Testcontainers
./mvnw verify -f modern/pom.xml

Both suites fail loudly if zero tests are discovered, and each rejects the other suite's stand flag instead of quietly running against the wrong target. Last measured on 2026-08-05: characterization 47/47 and E2E 34/34 green against both stands. The levels above these suites (unit, ArchUnit, Testcontainers integration, k6 load) and what each is for are described in docs/ENGINEERING_STANDARDS.md §3 and docs/deployment.md §5.

Deployment

Nothing is deployed. There is no running instance of either stand, no URL, no TLS certificate and no backup schedule — and this section will not describe steps for infrastructure that does not exist. The rule and its reasoning are in docs/deployment.md §10.

What exists today is the part a deployment needs and that can be verified locally: container images built by multi-stage Dockerfiles, an application healthcheck that actually fails when the database is gone, Flyway migrations that run on start, structured logs, optional OTLP tracing, and a reverse-proxy overlay carrying auth, security headers and rate limiting — each measured, see Where stage 6 stands. The host, the TLS termination, image publishing and backup/restore are open, and until they are done, stage 6 stays open with them.

Screenshots

Pending, deliberately. The screenshots this README should carry are of the two stands as deployed, side by side (docs/DEVIATIONS.md: "diagram and screenshots land with the deployed stands they should show"). Since no deployment happened, those screenshots do not exist, and no image path is referenced here that the repository cannot back up with a file. Both UIs render locally one docker compose up after the quickstart above; the architecture is the diagram, not a picture of a browser.

Honest limits

  • The legacy application is synthetic but pattern-faithful — built from real legacy smells, transparently catalogued (legacy/LEGACY_NOTES.md), because no suitable genuinely abandoned, permissively licensed OSS application exists (research documented in ADR-0001). The catalogue includes deliberate security warts — among them a flagged SQL-injection-shaped search (B4), fixed in the modern stand in stage 4 and told as the playbook's security story.
  • Small scale, disclosed exactly: ~1.7k LOC backend / 25 endpoints / 10 views. Numbers do not scale linearly to 500k-LOC systems; each playbook chapter states what does and does not generalize.
  • The safety net has a blind spot, and it was found the hard way. With a strict style-src 'self' at the edge, the E2E suite ran 32 of 34 green while the browser was blocking Angular's runtime-injected component styles. Selenium asserts behaviour and text, not appearance. It was found only by opening a real browser and reading the console; verify-edge.sh now pins script-src 'self' verbatim and states the blind spot in its own output. A green suite can prove less than it appears to.
  • The stands no longer share a database version (9.6 legacy vs. 18 modern). The orderings and the report payloads were measured equal on this seed, on 2026-08-05 — that is evidence, not a proof that collation cannot matter.
  • The load numbers are a comparison baseline, not a capacity statement: load generator, application and database shared one laptop, and the dataset is a 10-customer demo seed.
  • Effort figures are AI-agent wall-clock time (see How this was built); the playbook labels measured values and experience-based estimates separately.
  • AI-experiment results are model- and date-specific; the protocol pins both.
  • Known standards deviations are ledgered in docs/DEVIATIONS.md — nothing is silently waived.

Deutsche Kurzfassung

migration-lab ist eine öffentlich nachvollziehbare Legacy-Modernisierung: Java 8 / Spring Boot 1.5 / AngularJS → Java 25 / Spring Boot 4.1 / Angular 22.

Der professionell entscheidende Schritt kommt zuerst: ein Sicherheitsnetz aus Selenium-E2E-Suite und Charakterisierungs-Tests, das während der gesamten Migration grün bleiben muss. Jede Etappe ist ein auscheckbarer Git-Tag mit lauffähigem Docker-Compose-Stand. Sackgassen werden dokumentiert statt gelöscht, und das KI-Testgenerierungs-Experiment folgt einem vorab festgeschriebenen Protokoll mit Mutation-Testing-Auswertung (PIT).

Stand heute: Etappen 0–5 sind abgeschlossen, Etappe 6 (Betrieb und Härtung) läuft. Gemessen erledigt sind PostgreSQL 18, Flyway-Migrationen, aussagekräftige Health-Checks, strukturierte Logs mit optionalem Tracing, ein Reverse Proxy mit Authentifizierung, Security-Headern und Rate Limit sowie eine Last-Messbasis. Nicht erledigt ist die Inbetriebnahme selbst: Es läuft nichts öffentlich, es gibt keinen Server, kein TLS und keine Sicherungen — folglich existiert weder der Tag stage-6-cloud-ops noch ein Release v1.0.0. Das steht hier so, weil das Weglassen genau die Schönfärberei wäre, gegen die dieses Repository argumentiert.

Transparenz zur Entstehung: Die Umsetzung erfolgte KI-gestützt — ein Claude-Code-Agent hat unter Anleitung und Review des Inhabers gearbeitet. Die geloggten Stunden (docs/worklog.md) sind Agent-Wall-Time unter Aufsicht, keine Personentage eines Teams; was auf reale Projekte übertragbar ist (Methode, Stolperfallen, Entscheidungsregeln) und was nicht (die Stundenzahlen), steht oben unter How this was built und in jedem Playbook-Kapitel.

Das Ergebnis für Entscheider: ein deutschsprachiges Migrations-Playbook (playbook/) mit Vorgehen, Stolperfallen, transparent gekennzeichneten Aufwänden und Entscheidungsregeln — wiederverwendbar für reale Modernisierungsprojekte.

Ein Projekt von Stoicera Software Group · Lugmayr-Kern, Oberösterreich.

License

Apache-2.0

About

No description, website, or topics provided.

Resources

Security policy

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Used by

Contributors

Languages