Document the phase contract, permanent and temporary flags, controller restart boundary, rollback limits and required release evidence. This runbook does not grant permission to deploy.

Verification and release boundary

The latest clean-source mixed migration and process-evidence audit pass locally. The current wrapper suite passes 132 tests, with unchanged Kafka dependencies before and after the run. The reorganized Python suite passes 65 tests. These results apply to the complete candidate stack, not every intermediate commit. Focused tests are included with the relevant layers.

The final requirement audit and remote CI review remain open. Published artifact qualification, live production state, the client/tool floor, the deployed ZooKeeper server, capacity limits and named security/release approvals remain release gates. Do not deploy an intermediate stack commit.

@bringhurst
bringhurst added this pull request to stack #580 September 10, 2026 22:49
@bringhurst
bringhurst force-pushed the 3.9-li-bridge/runbook branch from de50167 to 67d7a2f Compare September 10, 2026 23:07
@bringhurst
bringhurst removed this pull request from stack #580 September 11, 2026 01:35
@bringhurst
bringhurst force-pushed the 3.9-li-bridge/runbook branch from 67d7a2f to ba1f4bf Compare September 11, 2026 01:35
@bringhurst
bringhurst added this pull request to stack #582 September 11, 2026 01:36
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Projects

None yet

Development

Successfully merging this pull request may close these issues.

1 participant